Numbers, data, facts
Urban planning expert opinion procedure | 2012 | |
Neighborhood development | 2014 | |
Preparation of design manuals | 2015/2016 | |
Decision on development plan | 2017 | |
Development of 1st construction phase | 2016 | |
Construction of Untere Wiesenterrasse | 2016 | |
Start of building construction 1st construction phase | 2017 | |
Market exploration procedure | September 2017 | |
Completion of parking lot on K2 | November 2021 | |
Completion of development 2nd construction phase | February 2022 | |
Creation of a sampling area for public roads, paths and squares |
November 2022 | |
Completion of the upper meadow terrace | April 2023 | |
Completion of lighting 1st construction phase | November 2023 | |
Start of work on the campus square (western promenade) |
November 2023 |
By using this function, you agree that the data may also be transferred to third countries, outside the European Economic Area, without an adequate level of data protection (especially USA). It is possible that authorities may access the data without any legal remedy. You can revoke your consent at any time. Further information: Privacy policy