Discover the new construction and conversion of the Käferschule with insights into the planning, contractors and interesting details such as the planned photovoltaic system. ">Discover the new construction and conversion of the Käferschule with insights into the planning, contractors and interesting details such as the planned photovoltaic system. ">

  • en
    • en
    • de
Filter Tags
Filter Tags
  • Internal pages
  • News
  • Documents (PDF)
  • External pages
  • All results
Search content

Beetle school - new building and conversion

Exterior view of the Beetle School
Exterior view of the Beetle School
  • Profile

    Start of construction: spring 2022

    Expectedcompletion of new construction: Summer 2023

    Estimated completion ofremodeling: Summer 2024

    Total costs: 7.000.000 Euro

  • Planners and contractors

    Planner

    Architect: Wob Consult (current)

    Structural engineer: LepkeIngenieurgesellschaft mbH&Co

    Soil expertise: Gesellschaft für Grundbau und Umwelttechnik

    Fire protection: IFB Schütte, Brandschutzberatung Kröger GmbH

    Electrical engineering: IB Schulz Ingenieurbüro

    Heating-Ventilation-Sanitary: INGENIEURBÜRO MEYER

    Kitchen planning: Scholz Planungsbüro für innovative commercial kitchens

    Acoustics: GTA -Gesellschaft für Technische Akustik mbH

    Outdoor facilities: Prisma Digital As-built survey,

    pro garten landscape architectsBresser Jablonka PartGmbB

    SiGeKo: IUP.engineers

    Building surveying: Vermessungsbüro Stein und

    Executing companies

    Shell construction: PARTNER BAU Quedlinburg GmbH

    Roofers: DachdeckereiMarco Schulze GmbH & Co. KG

    Scaffolding: Hibbeln GmbH

    Grounding and lightning protection: Wagener & Thormählen GmbH

    Power installation: Schröter Elektro-,

    Schalt- und Regeltechnik GmbH Hecklingen

    Light current installation: ABL GmbH & Co. KG

    Heating and plumbing: Spiller& Krüger GmbH & Co.KG

    Facade: GEBOthermGmbH,

    Thorsten Stielau carpentry and timber construction

    Metal construction and locksmith work: DaenickeStahl-Metallbau GmbH

    Screed: K B Böden GmbH

    Interior plaster: Weser BauputzGmbH

    Interior doors: Neiteler& Brand BauelemenetGmbH

    Cabinetmaker: Joinery Ludger Ostlinning

    Floor coverings: Company RAULFS GmbH,

    Tiles & Dry construction: Christian Noack


  • Description and status of the construction project

    New construction, conversion and expansion are planned until fall 2024.

    The project was completed in two construction phases from March of this year to October 2024. In the first stage, a new school building was constructed by July 2023. This was followed by the conversion and extension of the canteen from August 2023 to October 2024.

    The official inauguration took place on October 25, 2024 in the presence of the Lord Mayor.

    The new building contains six classrooms, four differentiation rooms and a therapy room for special activities. There is a spacious corridor area with play niches combined with large bay windows. It has bright, friendly classrooms with decentralized ventilation systems, sun protection and modern IT equipment for digital learning opportunities. Special attention is paid to accessibility in terms of room acoustics, elevator and automatic doors.

  • Interesting aspects

    There is a photovoltaic system on the roof, which contributes to climate protection and generates around 35,000 kWh of electricity per year. An information monitor in the break hall illustrates the topic for children and parents.

    • The foundations are poured - 05.04.2022

      The foundations are poured - 05.04.2022

      1 | 15
    • The first walls are up - 03.06.2022

      The first walls are up - 03.06.2022

      2 | 15
    • The ceiling elements are mounted - 04.07.2022

      The ceiling elements are mounted - 04.07.2022

      3 | 15
    • The upper concrete ceiling is poured- 26.08.2022

      The upper concrete ceiling is poured- 26.08.2022

      4 | 15
    • Topping out ceremony - 22.09.2022

      Topping out ceremony - 22.09.2022

      5 | 15
    • The roof is sealed

      The roof is sealed

      6 | 15
    • The windows are installed - 17.11.2022

      The windows are installed - 17.11.2022

      7 | 15
    • Installation of ceilings and floors in a classroom - 06.06.2023

      8 | 15
    • Ceiling substructure in the break hall - 13.06.2023

      9 | 15
    • Ceiling substructure in the hallway - 22.06.2023

      10 | 15
    • Advanced ceiling work - 22.06.2023

      11 | 15
    • Classroom with cabinet niches - 23.06.2023

      12 | 15
    • Exterior view of the school building - 27.06.2023

      13 | 15
    • Exterior view of the school building - 29.06.2023

      14 | 15
    • The flooring is laid - 29.06.2023

      15 | 15
    By using this function, you agree that the data may also be transferred to third countries, outside the European Economic Area, without an adequate level of data protection (especially USA). It is possible that authorities may access the data without any legal remedy. You can revoke your consent at any time. Further information: Privacy policy