Nordsteimker Straße
Construction work on schedule
Road marking work on the Nordsteimker Straße
Closure has to be extended for one day The construction work for the new cycle path along Nordsteimker Straße is on the home straight. The junction with Erich-Bammel-Weg has been fully closed since July 15 - this marks the final stage of the construction work, which has been ongoing since February. To ensure road safety on Nordsteimker Straße, it is necessary to renew the markings on the central reservation. In order to carry out the work, the current road closure will be extended for one day towards the end of the town. This means that on Saturday, July 27 only, the closure will also include the exits from Ahornweg and Kiefernweg. It will then not be possible to enter Nordsteimker Straße. From Sunday, July 28, Ahornweg and Kiefernweg will be accessible again as before. As a result, residents of Steimker Berg will only be able to leave the residential area by car via Unter den Eichen towards the city center on July 27. Wolfsburger Verkehrs Gesellschaft (WVG) will reroute bus services accordingly for this day. The existing traffic routing will remain in place until the end of the work in mid-August. Due to the full closure of the Nordsteimker Straße/Erich-Bammel-Weg junction, road users traveling into and out of the city will have to take the detour via Dieselstraße, Landesstraße 290 and Kreisstraße 111. |
The construction work will continue until mid-August. After that, the road will be open again. We are on schedule with the work.
We are building a new and wider cycle path along Nordsteimker Straße to make the route more attractive for cyclists. At the same time, LSW is laying new district heating pipes. We have coordinated the work so that the impact can be kept to a minimum.
We are on schedule. The current construction progress is around 65 percent. The final stage will start on July 15. The work will be completed by mid-August.
During the final stage, the entire area of the junction with Erich-Bammel-Weg will be renovated. This will require the road to be fully closed. This means that it will no longer be possible to drive not only out of town, but also into town via Nordsteimker Straße. Steimker Berg will then only be accessible again for residents from both sides. This will be from the city center via Unter den Eichen and from Nordsteimke via Ahornweg.
Residents of Nordsteimker Straße up to Erich-Bammel-Weg (petrol station, nursing home, petrol station) can be reached from Berliner Ring via the western section of Nordsteimker Straße. From the east, these residents can be reached via the detour route.
Both inbound and outbound traffic will be diverted via Berliner Ring, Dieselstraße, Zollstraße (L290, past Reislingen and Reislingen Süd-West) and the K111 in Nordsteimke.
From June 24 to July 12 (i.e. before the full closure of Nordsteimker Straße!), the road surface in the St. Annen junction area in the northbound direction (i.e. from the VfL stadium in the direction of the castle) will be repaired. The road in this direction will be closed from the junction Berliner Ring / Rothenfelder Straße (at the level of Edeka and the old VfL stadium) - neither Berliner Brücke, nor Heinrich-Nordhoff-Straße (Heßlinger Straße) and Dieselstraße will be directly accessible from the north from Berliner Ring. Traffic will be diverted accordingly.
Due to the fact that Dieselstraße is not accessible from Berliner Ring, we also have to adjust the detour for Nordsteimker Straße. The detour then leads via Reislinger Straße to the traffic circle, from the traffic circle via Käthe-Paulus-Straße back to Dieselstraße on the original detour.
Important: The St. Annen junction will be free again when Nordsteimker Straße is also closed in the direction of the city center.
No, the traffic lights coming from Sandkrugstraße will not be adjusted as this is not the official detour route.
From June 24 to July 15, residents of Steimker Berg coming from Berliner Ring will be directed via Reislinger Straße to the traffic circle and then northwards via Käthe-Paulus-Straße back to the original detour via Dieselstraße and Zollstraße.
From July 15, Steimker Berg will once again be directly accessible from both sides. The full closure will only begin after the "Unter den Eichen" junction coming from the Berliner Ring. This means that access from the city center is possible via the "Unter den Eichen" road and from the direction of Nordsteimke via the "Ahornweg".
Access to Steimker Berg is only permitted for local residents!
A resident is anyone who lives on a property adjacent to the road or has to go there to do something. This means that residents of Steimker Berg and their visitors/guests can drive into Steimker Berg. This also applies to customers of the adjacent businesses (for example the Parkhotel, the café or the physiotherapy practice). All others are prohibited from driving through.
Residents of Steimker Gärten are not authorized to drive through. It is therefore not permitted to drive through Steimker Berg.
The roads will be signposted with the traffic sign "No entry" and the addition "Residents free". In addition, the city reserves the right to carry out radar checks and, in coordination with the police, other traffic controls.
Drivers will be fined at least 50 euros for disregarding the no-entry sign.
Yes, the Steimker Berg can still be reached by bus. The current detour via Erich-Bammel-Weg will remain in place until July 15. From July 15, the bus will once again run regularly via Nordsteimker Straße and Alte Landstraße.
Cycle traffic in an east-west direction will be routed via the streets "Unter den Eichen" and "Ahornweg" through the Steimker Berg residential area. The detour is signposted.